MDT-4412Rotor Shaft 4.75"22d supply
Mud Motor Assembly
On hand: 3 → Order 20 EA
Order 20 units — lead time risk. Current stock covers only 22 days against a 14-day lead time with no safety buffer.
MDT-4416O-Ring Kit24d supply
Mud Motor Assembly
On hand: 8 → Order 30 KT
Order 30 units — high-velocity consumable below reorder point. 7-day lead time offers quick replenishment.
MDT-4413Stator Housing30d supply
Mud Motor Assembly
On hand: 3 → Order 15 EA
Order 15 units — demand trending up 12%. Lead time risk at current stock level.
JAR-3302Anvil Assembly36d supply
Drilling Jar Assembly
On hand: 1 → Order 6 EA
Order 6 units — single unit on hand with 14-day lead time. Any unexpected demand causes immediate stockout.
STB-2204Set Screw Kit38d supply
Stabilizer Sub Assembly
On hand: 5 → Order 12 KT
Monitor closely — order within 30 days.
STB-2202Mandrel Body40d supply
Stabilizer Sub Assembly
On hand: 2 → Order 8 EA
Order 8 units — 21-day lead time with only 40 days of supply. Risk of stockout on next large order.
JAR-3303Mandrel Seal Kit46d supply
Drilling Jar Assembly
On hand: 3 → Order 10 KT
Monitor closely — order within 30 days.
MDT-4414Bearing Pack73d supply
Mud Motor Assembly
On hand: 12 → Order 10 EA
Monitor closely — order within 30 days.